题目

If 20 diggers, each working at the same constant rate, can dig a 100-meter long trench in hard soil in 3 days, how many diggers are needed to dig a 180-meter long trench in soft soil in the same 3 days, given that a digger is 20% more productive in soft soil than in hard soil?


选项

A.

25

B.

28

C.

29

D.

30

E.

32

解析

20名挖掘工在硬土中挖100米长的沟渠需要3天。 1名挖掘工在硬土中3天可以挖\( \frac{100}{20} = 5 \)米长的沟渠。 由于软土中效率提升20%,1名挖掘工在软土中3天可以挖\( 5 × 1.2 = 6 \)米。 因此,要在3天内于软土中挖180米长的沟渠,需要的挖掘工数量为:\( \frac{180}{6} = 30 \)名。 答案:D
在线客服
官方微信
公众号